HomeNewsWilliamstown NewsMonroe Township places emphasis on improving roads

Monroe Township places emphasis on improving roads

Officials discuss putting $6.8 million into repaving, repairing, reconstructing roadways

Monroe Township has acknowledged the roads need work and has a plan in place to repair, repave and, in some cases, reconstruct roads in town.

The township has a six-year capital program that anticipates all projects and funding requirements for the township. The road program is listed in the six-year capital program as a six-year, $6.8 million project that should be completed in 2023.

“Our goal is to continue to invest and plan for the future,” Councilman Cody Miller said. “Before my term on council, we had no roads paving program. Through the work of countless individuals, council and the mayor, we were able to start the process.”

Adams, Rehmann & Heggan Associates, Inc., a civil engineering and land surveying company, visited 531 stretches of road in the township and graded them on a scale of 0–100. Roads that were graded between 0 and 54.99 are considered past the point of repair and should be reconstructed. Roads graded between 55 and 74.99 should be milled a minimum of two inches and overlaid. The other option is to pulverize, stabilize and overlay the road. Roads graded between 75 and 89.99 should be either seal treated or a 1.25-inch overlay should be applied. Finally, roads graded between 90 and 100 should be maintained by the department of public works.

To come up with the score, ARH put in more than 100 hours of investigation on the township’s roadway network. It would check the roads for transverse cracks, longitudinal cracks, alligator cracks, potholes and deficient drainage. ARH would rate each of those five aspects on a scale of 0–3 with 0 being no deficiencies and 3 being serious deficiencies. The sum of those five will be multiplied by four.

The second part of the rating is checking shrinkage cracks, corrugations, ravelling, polished aggregate, rutting, shoving or pushing, excess asphalt and overall riding quality. The same 0 to 3 score as above but the sum of those eight will be multiplied by 1.67. The two products are to be added together — that number will be subtracted by 100 to give the final score.

Per the capital plan, in fiscal year 2017, the township had plans to reconstruct roughly one half of a mile of South Shore Drive, while milling and overlaying parts of Kirkwall Drive and Forest Drive.

In fiscal year 2018, the second phase of reconstructing South Shore Drive is planned to be reconstructed, while stretches of Kent Road, Ireland Terrace and Avery Drive have plans to be milled and overlaid. The second phase of Forest Drive, mill and overlay, should be completed as well.

Fiscal year 2019 contains plans to reconstruct one-third of a mile of Laurel Avenue and the milling and overlay of Whispering Woods Drive. The second phase of Flannigan Avenue is slated to receive a two-inch overlay as well.

In year four, fiscal year 2020, there are plans to reconstruct more than one half of a mile on Magnolia Avenue, wedge mill and overlay parts of Holiday City Boulevard and Whispering Woods Drive, and have a two-inch overlay on Herbert Avenue.

In the final year of the project there are plans to mill and overlay almost one mile of Whitehall Road, a two-inch overlay on Herbert Avenue and wedge mill and overlay of Whispering Woods Drive phase three.

The five-year capital road program is a fluid plan. Listed above is a recommendation, at any point a road could be moved up a year or down a year.

For more information on the road program in Monroe Township, the department of public works can be reached at (856) 629–4444.

ANTHONY J MAZZIOTTI III
ANTHONY J MAZZIOTTI III
Anthony is a graduate of Rowan University and a proud freelance contributor for 08108 magazine. He has past bylines in The Sun Newspapers and the Burlington County Times.
RELATED ARTICLES

Related articles

2

Williamstown Calendar
October 1, 2024

3

A new place
September 30, 2024

5

Arts and crafts
September 29, 2024

6

7

First day of school
September 25, 2024

8

Williamstown Calendar
September 24, 2024

9

Williamstown Calendar
September 17, 2024

11

Grant funds
September 14, 2024

13

Taking the wheel
September 11, 2024

14

Williamstown Calendar
September 10, 2024

16

Making music
September 6, 2024

18

Williamstown Calendar
September 3, 2024

19

21

Ice-cold stop
September 1, 2024

22

Daisy nurses
August 31, 2024

25

Williamstown Calendar
August 27, 2024

28

‘Yappy’ hour
August 23, 2024

31

Williamstown Calendar
August 20, 2024

32

A night out
August 15, 2024

33

Williamstown Calendar
August 13, 2024

36

Welcome, officers
August 6, 2024

37

38

Melodies on Main
August 4, 2024

39

Squeaky clean
August 3, 2024

40

current issue

latest news

Newsletter

How to reach us